Master Bathroom Plumbing Re-route and Root Mitigation via CIPP

Root infiltration identified at the main clean-out and extending beneath the foundation into the master bathroom line, complicated by encroaching vegetation and substandard electrical conduit depth.

August 31, 2026

Service Area
University Park
Typical Cost
$3,400–$4,600
Duration
2-3 days

The Problem

Warning signs

  • Slow drainage in master bathroom, gurgling sounds in the toilet when other fixtures are used, or visible sewage backup at the exterior clean-out.

Our Diagnosis

Visual inspection of the rear clean-out revealed a large root penetrating a pipe joint. Further scoping showed the root mass extending past the foundation wall to the first interior elbow.

Root cause

Tree root intrusion into aged pipe joints, exacerbated by a large tree located near the sewer line path.

How We Fixed It

  1. 1

    Removed and ground the stump of the interfering tree to prevent future growth. 2. Excavated the existing exterior clean-out. 3. Hydro-cleaned the pipe to remove existing root masses. 4. Installed Cured-In-Place Pipe (CIPP) lining from the exterior access point to bridge the damaged joints under the foundation. 5. Installed a new 2-way PVC clean-out for future maintenance access.

How to Prevent This

  • Avoid planting large-growth trees within 10 feet of sewer laterals and perform annual camera inspections if historical root issues exist.

Materials Used

  • CIPP Lining Resin and Felt
  • 2-Way PVC Clean-out Assembly
  • PVC Pipe and Fittings
  • Root Killer Chemical Treatment